Inpatient Rehab Facility

 


A New Haven, CT residential treatment center was in need of a reliable backup power system. They were looking to provide a safe environment for their clients in the event of a power outage. The three-story buildings and mature plantings made the typical methods of delivery and placement impossible. So, we utilized a 200-foot crane to lift the 2600lb Cummins C80 diesel generator with an ASCO 300 Series Transfer Switch over everything in order to safely place it on the concrete pad. Our client now has the much-needed standby power system that will offer protection for their patients and the facility. This delivery method and installation caused minimal interruption for their entire operation.